- Consists of handover of the equipment package(s) to Client
- Occurs after successful Factory Acceptance Testing (FAT) has been carried out and documented according to contract requirements
- Final documentation is prepared with a focus on consistency check and verification and delivered in accordance with the contract
- To formalize the take-over of the equipment package(s), a take-over meeting is arranged with the Client and both parties sign a commercial take-over certificate